CLOSING SERIAL TITLES
Revised: February 1996
Selector decides that the title is no longer wanted. Letter is written to the source to cancel the order.
Title is no longer being published.
A title is "dropped" if:
- we cannot confirm whether it is still available (e.g. no reply to claims)
- the title is no longer available on a gift or exchange arrangement.
No letter is sent to source. If material starts coming again, the records are automatically re-opened without referral to selector.
NOTE: Closings due to title changes or series treatment changes are not covered in this procedure. See appropriate sections of the Berkeley Processing Manual.
CEASES AND DROPS INITIATED BY THE BRANCH LIBRARY:
Branch does the following updating REGARDLESS OF RECEIVING LOCATION.
INNOPAC ORDER RECORD:
e.g. 2/95 Faxon reports ceased with v.12 dj/publ 3/95 DROP per MT/BUSI no longer avail. as gift km/busi 5/95 DROP/no reply to claims dj/publ
INNOPAC CHECKIN RECORD
If all issues have been received:
Because of space limitations in INNOPAC, the checkin record should be deleted as soon as it is no longer needed for processing purposes. Whenever possible, binding should be completed at the point of closing so that the record can be eliminated. IF CHECKIN RECORD MUST BE RETAINED, annotate it as in 2b below.
If further issues due on order:
- UPLOAD = D
- Delete checkin boxes for any issues no longer due on order
- Insert final "null box" with note "CEASED" or "DROPPED"
- Optional: add check note for special routing instructions
e.g. Hand to ... when all issues received
- Bind if appropriate
- Delete checkin record and card
GLADIS
Close SUM field:
NOTIFY CATALOGING UNIT:
If CEASE of a CATALOGED serial set:
- Notify Serials Cataloging Division via printout or correspondence annotated with GLADIS #, INNOPAC order #, or INNOPAC bib #.
- Do not notify cataloging units of the following:
--ceases of uncataloged titles, MVMs, or seps
--drops (regardless of cataloging treatment)- IF RLOC=E:
Notify East Asian Library to close its manual checkin records.
Central processing unit does the following:
Branch performs the following actions after notification received from central processing unit:
If more issues due on order:
When all issues received:
PURCHASES, GIFTS, LC FOREIGN ACQUISITION PROGRAM
Payments Unit performs steps 1-3, 5
BPU performs step 4 for MAIN serials.
- Changes status to z
- Inserts ven. note
- Send copy 1 of cancellation letter to vendor; keep copy 2 for Payments files.
- Change UPLOAD to "D"
- Delete checkin boxes for any issues no longer due on order
- Insert final null box with note "CANCELLED"
- If claiming necessary and/or more issues due on order:
-- Claim if appropriate
-- If RLOC=S: insert CHECK NOTE: "Refer to BPU when all issues received or claiming complete"
Make printout of INNOPAC checkin record and route as follows:
- MAIN: to BPU (use special cancellation project box next to BPU box)
- SUBJECT SPECIALTY LIBRARY: to SUBJECT SPECIALTY LIBRARY
- DO NOT notify Serials Cataloging Division
- For WITHDRAWLS and MVM's -- notify Serials Records/Documents (SerDoc)
SetsSEPS and MVMs
- Pull unbound material from stacks
- Bind as appropriate
- Eliminate INNOPAC Checkin record and card
- Update GLADIS:
-- Close SUM field (do not use //
-- Delete CI field
-- Update SHL and V/C fields as appropriate
- Eliminate INNOPAC Checkin record and card
- Delete CI field from GLADIS
**Full procedures under development**
For Serials Payments Staff:
EXCHANGES (acqtype=x)
Branch does the following updating before notifying Exchange Division to cancel order:
INNOPAC ORDER RECORD
- Change STATUS to Z
- Insert INTERNAL NOTE (tag=n):
e.g. 2/5/96 CANCELLED per PUBL/TA- Notify Exchange Division to cancel order
INNOPAC CHECKIN RECORD & GLADIS
- If all issues have been received:
-- Bind if appropriate
-- Delete checkin record and card
(If record must be retained, annotate it as in 2b below)
-- Update GLADIS
-- Close SUM field (do not use //)
-- Delete CI field
-- Update SHL and V/C fields as appropriate- If further issues due on order:
-- Claim as necessary
-- Update the checkin record as follows:
-- Change UPLOAD to D
-- Delete checkin boxes for any issues no longer due on order
-- Insert final null box with note "CANCELLED"
-- Optional: insert check note for special routing instructions
e.g. Hand to ... when all issues received- When all issues have been received or claiming complete:
-- Bind if appropriate
-- Delete checkin record and card
-- Update GLADIS
-- Close SUM field (do not use //)
-- Delete CI field
-- Update SHL and V/C as necessary
CEASES AND DROPS INITIATED BY THE BRANCH LIBRARY
CEASES AND DROPS INITIATED BY CENTRAL PROCESSING UNIT:
Central processing unit does the INNOPAC work; refers to cataloging units as appropriate; and notifies branch via correspondence or printout.
Branch performs the following actions: